Experience
Interim Project Manager
IT services company of a regional energy supplier
- Delivery of various end-customer projects in server and network infrastructure on time, in quality, and within budget.
- Project 1: Firewall renewal, replacement of an ASA firewall with a Fortinet firewall at an automotive supplier.
- Project 2: Migration of file services from dedicated servers at 5 branch locations into a central managed file service, including DHCP, directory, and print services, as well as decommissioning of the old domain controllers.
- Project 3: Renewal of the network infrastructure at the headquarters and branch locations of a logistics company and transition of the LAN, WLAN, and firewall environments into a managed network service.
- Project 4: Network renewal, replacement of the core and access switches at the headquarters of a medical technology company and transition into a managed network service.
- Project 5: Firewall renewal, replacement of an ASA firewall with a Fortinet firewall for a city.
- Environment: ASA and Fortinet firewalls, Cisco network components, ITSM Heat/Ivanti, Confluence.
Project Manager
IT service provider for Finanz Informatik
- Increase of the security level through consistent CIS hardening and proof of technical compliance.
- Hardening of about 7,500 IT assets from different technologies in all stages of an end customer according to CIS benchmark requirements.
- Definition and alignment of the project scope with all relevant stakeholders.
- Setup of the project organization including governance, processes, and documentation standards.
- Creation and maintenance of high-level and detailed plans with MS Project.
- Management of the PMO team consisting of project management and PMO staff.
- Ensuring quality, deadlines, and resource use.
- Structuring of CIs by technology and assignment to CIS benchmarks.
- Definition and maintenance of Qualys profiles and policies.
- Execution of target-to-target checks for non-Qualys controls.
- Planning, control, and quality assurance of Qualys scans before and after hardening.
- Close alignment with the business units for planning and implementation of the hardening measures.
- Support and coordination of the required changes in operations.
- Provision of quality-assured evidence such as scan reports, deviation documentation, and target-to-target checks.
- Setup of transparent reporting on CIs, technologies, and work packages.
- Regular reporting to committees and top management.
- Ensuring acceptance and handover of all project results.
- Setup and maintenance of the risk register, including derivation and follow-up of measures as well as escalation and decision management.
- Environment: CIS benchmarks / hardening standards, CMDB-based CI structures, Qualys compliance scans, about 7,500 IT assets, hardening of server operating systems, middleware, databases, and network components, involvement of about 22 departments and more than 130 project members, classic and hybrid project management.
- Tools: MS Project, Excel, SharePoint, Microsoft 365, ServiceNow (CMDB, Change, Workflow), MS PowerPoint, Think Cell.
Security Analyst IT Risk / Project Manager
French major bank
- Ensuring security compliance for IT applications in the context of DORA compliance.
- Design of the end-to-end process to ensure the security compliance of IT applications.
- Review and assessment of IT application risk profiles with regard to the CIAT criteria (confidentiality, integrity, availability, traceability).
- Definition of the application security baseline by selecting relevant IT security controls for the respective risk profile.
- Conducting security compliance reviews with IT application owners through interviews or workshops.
- Conducting gap analyses to identify risks from not meeting the IT security requirements.
- Validation of the compliance review results and risk findings with security managers and the CISO.
- Formulation of risk-mitigating measures and documentation in the bank's GRC tool.
- Follow-up of measures and alignment of evidence.
- Environment: ServiceNow GRC, NIST Cyber Security Framework, ISO 27001, ISO 27005, DORA.
Project Manager
Municipal energy supplier
- Further development, upgrades, and migrations of geoinformation systems to reduce costs.
- Lovion consolidation project: consolidation of the Lovion network construction system and the Lovion Work Management System, including project planning, interface management with business units, and coordination of software development and data center service providers.
- Smallworld GIS upgrade project: upgrade from version 4.3.08 to 5.3.3, including migration management and setup of the new virtual server infrastructure.
- ETRS89 migration project: conversion of the coordinate system from Gauß-Krüger GK2 to ETRS89.
- Alarm platform project: introduction of a central alarm platform based on the FE2 solution from Alamos.
- Delivery of eight additional small projects in the geo-information environment.
- Environment: Lovion system, GE Smallworld GIS, classic and hybrid project management.
- Tools: Jira, Confluence, Xray, AWS, VMware ESX.
Project Manager, Coach, Sparring Partner
Financial services provider for securities trading
- Upgrade of the BMC ITSM suite, including the release-related move of the infrastructure platform to Native Cloud (Kubernetes).
- Ensuring the application's support capability through the upgrade.
- Coaching the internal project manager in creating project requests and project change requests.
- Support with project planning (milestones, resources, costs, budget).
- Coaching in project control, risk management, and escalation management.
- Support with project status reporting to management.
- Environment: Native Cloud (Kubernetes), BMC ITSM suite, BMC Helix.
Project Manager
Financial services provider for securities transactions
- Migration of 450 on-premise application servers to the Finance Cloud to reduce costs.
- Review of technical requirements and cloud compatibility of the application servers.
- Coordination of commercial as well as ordering and provisioning processes with the IT service provider.
- Execution of a proof of concept for process and technical migration.
- Support for application owners with ordering, technical questions, as well as termination and decommissioning of legacy devices.
- Regular reporting on achieved savings to management and IT controlling.
- Introduction of a Software Asset Management (SAM) tool to close audit findings.
- Budget planning, project planning, and control incl. milestone, resource, and cost plans.
- Coordination of internal staff and external service providers for project delivery.
- Participation in contract negotiations with service providers.
- Management of the implementation of the SAM tool Flexera for automated inventory management.
- Connection of the tool to data sources such as SCCM, AD, and CMDB.
- Implementation of IT Service Management processes and creation of operations manuals as well as security and test concepts.
- Operationalization of the license/software asset management process through the introduction of a SAM service.
- Onboarding of vendors and preparation of commercial contract and license data.
- Execution of license reconciliations and tracking of measures to close audit findings.
- Environment: Windows/Linux servers, Finance Cloud, FlexNet Manager Suite (FNMS) Flexera, SAP CUNO, planningIT, native cloud, classic and hybrid project management.
IT Security Project Manager
Insurance company in Austria
- Planning and implementation of IT security projects to mitigate cyber and information risks in line with DORA, VAIT, and FMA requirements.
- Project planning, control, and creation of milestone, resource, and cost plans.
- Coordination of external service providers and status reporting to management and steering committees.
- Implementation of an Intrusion Prevention System (IPS) and introduction of PKI certificate management for Active Directories.
- Introduction of a Data Loss Prevention (DLP) system based on Microsoft 365.
- Introduction of certificate checking for client-based VPN access and SSL inspection for encrypted internet connections.
- Support with IT compliance audits.
- Introduction of a Cloud Access Security Broker (CASB) solution incl. RFI, RFP, and proof of concept.
- Creation of a ransomware incident response playbook and development of a SOC target operating model.
- Modeling of the security incident response process and integration into the group IT incident management process.
- Development of a concept for implementing a group-wide parent CMDB.
- Environment: Clarity PPM, Jira, Confluence, Ariba, RSA-Archer, Microsoft Azure, Microsoft 365.
IT Project Manager
IT service provider for Finanz Informatik
- Setup and relocation of a data center incl. replacement of an existing data center and migration of customer IT systems.
- Main contact for the network department and responsible for providing the network infrastructure in the new data center.
- Coordination of around 20-25 employees for design, planning, and setup of the network.
- Moderation of workshops to develop migration concepts for different networks.
- Planning of the network setup in coordination with storage, server systems, and mainframe areas.
- Planning the relocation of firewalls, load balancers, and network management systems.
- Management of external service providers for data center interconnections.
- Implementation of IT security measures to close ECB findings in the area of network infrastructure.
- Implementation of line encryption on cross-connections between data centers.
- Implementation of network segmentation and protection through firewalls as well as securing the stock exchange connection.
- Tracking of measures and regular status updates to the customer.
- Environment: data center network infrastructure, DWDM, Application Centric Infrastructure (ACI), Fortinet/Cisco firewalls, load balancers, LAN, WAN, MAN.
Project Manager / Business Analyst IT Security & Business Continuity / Operating Model
French major bank
- Introduction of a NIST-based cyber security framework in four German entities to reach maturity level 3.
- Execution of control assessments incl. evidence collection and maturity level assessment for over 1,000 controls.
- Setup of a business continuity solution for emergency workstations (Business Recovery Seats) incl. site evaluation and provider onboarding.
- Introduction of the group-wide IT continuity framework and execution of business impact analyses.
- Execution of application and third-party risk analyses in line with BAIT and MaRisk.
- Introduction of a Secure Software Development Framework (SSDF) in line with NIST.
- Design of a cross-functional IT risk management organization and development of the target operating model (TOM).
- Project management for the stream operating model, organization, and governance to consolidate IT operations.
- Development of the target organization in coordination with HR and works councils.
- Support for the program manager as PMO incl. creation of business cases and milestone plans.
- Environment: RSA-Archer, NIST Maturity Assessment Tool, ISO 27001, ISO 27005, BAIT, MaRisk.
IT Transition Manager
IT service provider for Finanz Informatik
- Execution of a service provider change to transfer network and desktop services.
- Main contact for all transition-related topics.
- Coordination and alignment of all necessary activities for service transfer.
- Resource coordination and monitoring of contractually agreed support services.
- Environment: worldwide WAN of a bank, Cisco network components.
Project Manager Cyber Security
Deutsche Großbank
- Project management for the expansion of the ArcSight SIEM environment and transfer into Cyber Security operations.
- End-to-end implementation of ArcSight content onboarding projects based on protection needs analyses.
- Management of migration projects for ArcSight EMS and Reporting Manager.
- Optimization of the content onboarding process in coordination with SOC and Engineering.
- Management of a project to map the onboarding process in the BPM tool TIGGS, including building the CMDB.
- Elimination of audit findings in the area of Security Event Monitoring and vendor governance.
- Planning of the content migration from ArcSight to Splunk.
- Project management for security hardening: review of hardening policies, execution of gap analyses for IT governance, and definition of a requirements catalog.
- Coordination of assessment and review workshops with subject matter experts.
- Environment: HP ArcSight Enterprise Manager, TIGGS, MS SharePoint, RSA Archer, Remedy, ServiceNow, Splunk Enterprise, globally distributed virtual teams.
Service Transition Manager
Aviation / Air-Cargo
- Operational transition for a new central air cargo logistics handling system.
- Ensuring proper transfer into IT operations.
- Single point of contact for the system integration project team regarding service transition.
- Project planning, control, and monitoring of the operational transition in terms of timeline, scope, and budget.
- Coordination of sub-project managers as part of the operational handover.
- Content design of the operational handover process together with operations organizations.
- Organization and management of the Operational Review Boards.
- Environment: Replacement of a host-based system with air cargo management software, migration of around 50 supplier and acceptance systems.
Service Transition Manager / Change Manager
Deutsche Großbank
- Ensuring the proper transfer of software developments into operations as part of a bank integration.
- Definition of the Target Operating Model (TOM) and determination of resource needs.
- Alignment of Service Level Requirements, OLAs, and SLAs.
- Monitoring of quality gates in the waterfall model and delivery of documentation.
- Support in creating operations manuals, escalation matrices, and incident classifications.
- Planning of knowledge transfer for support levels 1 to 3.
- Responsibility for Operational Acceptance Tests and review of operational readiness.
- Introduction and operation of the SAP high-performance platform Magellan.
- Monitoring of changes in the production environment.
- Organization and execution of Change Advisory Boards (CABs) and approval of change requests.
- Environment: software development in Sales/Investments, SAP core banking system (UC4, ETL), BMC Remedy.
Project Manager
Internationaler Mobilfunk- Dienstleister
- Setup of a reporting process for revenue and profit (Revenue, P&L) between a subsidiary and the parent company as part of a company integration.
- Coordination of all activities to integrate the areas on time and within budget.
- Execution of a feasibility study with different options.
- Definition of milestones and responsibilities in the project team.
- Setup and integration of the reporting structure into existing systems.
- Reporting to project sponsors as well as Global Sales and Finance Management.
- Environment: merchandise management and financial systems, international project environment.
Sabbatical / Stay Abroad
Privat
- Sabbatical and stay abroad.
Project Management / Organization / Coordination
Deutsche Großbank / Bereich Application Integration Windows
- Provision of application servers for the migration of applications as part of a bank integration.
- Single point of contact for the Application Integration Windows team for the integration project.
- Clarification of project requirements for integration services for server applications.
- Coordination of incoming order requirements and commissioning processes.
- Resource planning and control to ensure order fulfillment.
- Interface to change and release management.
- Provision of automated applications in test environments for integration tests and production release.
- Environment: Windows 2003 Server, Active Directory 2003, NetInstall 5.7, MSI technology, Peregrine Service Center 6.1.
Outsourcing Project Manager - Transformation Phase
Internationaler Telekommunikationsdienstleister / Genussmittel Hersteller
- Global network and telecommunications outsourcing at 600 sites worldwide.
- Implementation of a standardized network environment (WAN, MAN, LAN, WLAN) and IP telephony at two factory sites in Germany as well as in Baltic and Nordic countries.
- Moderation of workshops to identify technical requirements and develop migration strategies.
- Definition of site requirements regarding power supply, cabling, and air conditioning.
- Collaboration with solution architects to determine equipment needs.
- Monitoring of hardware and software deliveries as well as technical concepts.
- Pilot and rollout of new infrastructure solutions.
- Negotiation of maintenance windows for migrations in 7x24h factory production environments.
- Management of acceptance tests and documentation of the new environment.
- Multi-project management of up to 11 parallel projects.
- Environment: Cisco network and IPT equipment, MS Project.
Release Manager
Internationaler IT- Dienstleister / Deutsche Großbank
- Transfer of release management processes from the bank to the IT service provider as part of desktop outsourcing.
- Knowledge transfer of processes and methods through interviews and shadowing.
- Documentation and optimization of release management processes and interfaces.
- Assumption of execution responsibility as release manager on behalf of the service provider.
- Coordination with change management processes according to ITIL.
- Environment: Peregrine Service Center 5.1/6.1, workflow management tool ADIS.
Migration Manager (Subproject Manager)
Deutsche Großbank
- Migration of application servers from an NT 4.0 structure to a Windows 2003 Active Directory structure in the investment banking area.
- Technical and organizational responsibility for approx. 250 application servers and 80 bank applications at the London site.
- Interface between infrastructure, operations, and product owners.
- Scheduling and status reporting to overall project management and customers.
- Provision of test, pre-live, and production environments via NetInstall 5.7.
- Preparation and support of acceptance tests as well as production go-live support.
- Design and optimization of supporting processes.
- Environment: Active Directory 2003, Windows 2003 Server, NetInstall 5.7, Peregrine Service Center 5.1/6.1.
Consultant / Analyst
Deutsche Großbank
- Management consulting to ensure internal and external IT compliance in the area of Enterprise Content Management.
- Creation of audit-proof system documentation (operations, security, and emergency concepts).
- Review of IT baseline protection according to BSI for newly introduced content management systems.
- Analysis and optimization of IT operations processes according to ITIL best practices.
- Modeling of business processes for automated document processing in ARIS.
- Planning of cross-functional segregation of duties between development and operations.
- Creation of training concepts, cost plans, and schedules for project implementation.
- Environment: AIX, Windows Server 2003, OS/2, MVS host, ARIS Toolset, BSI baseline protection.
Senior Consultant
ECS Bad Homburg GmbH
- Set up and led a bid management team for the consulting department.
- Qualified customer inquiries and developed solution concepts with subject matter experts.
- Created offers as well as handled price and contract negotiations.
- Managed resources, including qualification and procurement of external resources.
- Acquired and maintained relationships with suppliers and staffing service providers.
- Responsible for project calculations, controlling, invoicing, and management reporting.
- Introduced project management methods and tools.
- Supported pre-sales and business development.
Sub-Project Manager User Survey / PC Rollout
Unisys Deutschland GmbH
- Led the site and user survey workstream for a Europe-wide PC standardization project at a chemical company.
- Rolled out 38,000 client PCs across Europe.
- Collected inventory data manually through user interviews (200 PCs/day).
- Built an organizational structure with team lead level and managed up to 120 employees.
- Planned and carried out training measures.
- Reported status to the overall project management and handled escalations.
- Developed quality assurance measures.
- Environment: Windows XP, Radia software distribution, Bluecurrent rollout tool, MS Project.
IT Consultant / Management Consultant
Unisys Deutschland GmbH
- Qualified providers for a network outsourcing project in South America, Australia/New Zealand, and Europe.
- Prepared tender documents (RFI + RFP).
- Conducted the provider qualification process for a global MPLS network.
- Evaluated service provider offers and created a benchmarking matrix.
- Led service and price negotiations with shortlisted providers.
- Prepared decision papers for management.
Sub-Project Manager
Unisys Deutschland GmbH
- Set up the network and server infrastructure for a service center for automated document processing.
- Planned and designed the data center network infrastructure as well as WAN connectivity for 11 branch offices.
- Coordinated suppliers and accepted implementations (UPS, Cisco components, racks).
- Managed the relocation of around 30 server systems and 50 client workstations.
- Put the environment into operation together with the customer.
- Environment: Windows NT 4.0/2000 Server, Unisys document scanning lines, Cisco routers/switches.
Project Manager
m+s Elektronik AG
- Europe-wide rollout and operation of securities trading systems for Deutsche Börse.
- Rollout of EUREX, XETRA, and CBOT trading systems.
- Set up a helpdesk for remote monitoring and administration of the systems (5 x 18 hrs.).
- Led the nine-person international support and rollout team.
- Ensured compliance with SLAs.
- Environment: Windows NT 4.0, SUN Solaris, HP AIX, BMC Patrol.
Industry experience
See where this freelancer has spent most of their professional time.
Experienced in Banking and Finance, Information Technology, Telecommunication, Transportation, Food and Beverage, and Professional Services.
Business area experience
See which departments and functions this freelancer has contributed to most.
Experienced in Project Management, Information Technology, Operations, Quality Assurance, Procurement, and Sales.
Frequently asked questions
Have questions? Find more information here.
Robert is based in Kriftel, Germany.
Robert speaks the following languages: German (Native), English (Advanced), Hungarian (Advanced).
Robert has at least 24 years of experience. During this time, Robert has worked in at least 21 different roles and for 17 different companies. The average length of individual experience is 1 year. Note that Robert may not have shared all experience and actually has more experience.
Based on recent experience, Robert would be well-suited for roles such as: Interim Project Manager, Project Manager, Security Analyst IT Risk / Project Manager.
Robert's most recent position is Interim Project Manager at IT services company of a regional energy supplier.
In recent years, Robert has worked for IT services company of a regional energy supplier, IT service provider for Finanz Informatik, French major bank, Municipal energy supplier, and Financial services provider for securities trading.
Robert is most experienced in industries like Banking and Finance, Information Technology, and Telecommunication. Robert also has some experience in Food and Beverage, Professional Services, and Chemical.
Robert is most experienced in business areas like Project Management, Information Technology, and Operations. Robert also has some experience in Quality Assurance, Procurement, and Sales.
Robert has recently worked in industries like Banking and Finance, Utilities, and Information Technology.
Robert has recently worked in business areas like Information Technology, Project Management, and Quality Assurance.
Robert holds a Bachelor in Electrical Engineering, specializing in Communications Engineering from University of Applied Sciences of Deutsche Bundespost Telekom in Dieburg.
Robert has 11 certificates. Among them, these include: Certified NIS2 Directive 2.0 Lead Implementer, Certified Information System Auditor, and ISO/IEC 27001 Lead Implementer.
Robert is immediately available full-time for suitable projects.
Daily rate distribution
The rates shown represent the typical market range for freelancers in this position based on recent contracts on our platform.
Average rates for similar positions
Rates are based on recent contracts and do not include FRATCH margin.
The average daily rate is the mean of all daily rates from recent contracts of comparable freelancers on our platform.
The median daily rate is the middle value of all daily rates — half of comparable freelancers charge less, half charge more. Unlike the average, it is barely affected by outliers.
Calculated based on our freelancers’ daily rates as of 25 Nov 2026. Actual rates may vary depending on seniority level, experience, skill specialization, project complexity, and engagement length.
Similar freelancers
Discover other experts with similar qualifications and experience
Nikolaus B.
Last position:
Information Security, IS-Governance & Crossfunctional Governance at Zürich Beteiligungs-AG (Deutschland)
- Conducted security assessments for supplier qualification, business unit onboarding, and ongoing reviews of service providers and partners (Ongoing Assurance).
- Assessed technical and organizational measures (TOMs) against GDPR and information security requirements.
- Handled security reviews and approval processes in the Global Approval Navigator (OneTrust).
- Advised business units and IT on information security, security requirements, and risk-appropriate measures.
- Supported the development of SOC/SIEM processes and tools as part of the ISMS in line with ISO/IEC 27001.
- Analyzed cyber threats and coordinated security objectives and measures to address Security Findings with the SOC team.
- Monitored and assessed current security advisories and security-related metrics (KPIs).
- Reviewed, assessed risks, and approved exception requests (Security Exceptions).
- Independently analyzed and handled Security Events and supported the handling of security incidents.
- Planned and supported awareness initiatives to strengthen security awareness.
- Created, implemented, and reviewed information security policies and standards.
- Conducted protection needs analyses and gap assessments to identify security gaps and risk deviations.
- Defined and reviewed technical and organizational risk treatment measures.
- Advised on Third Party Governance with consideration of DORA, ISO/IEC 27001, ISO/IEC 27005, ISO/IEC 42001, and BCM in line with ISO 22301.
Frank J.
Last position:
Senior Project Manager / IT Manager - Email Gateway Migration & Information Security at Public Authority
- Strategic planning, detailed technical preparation and operational management of an email gateway migration in a security-critical government environment.
- Preparation of the technical specification and development of technical concepts and migration approaches in line with BSI requirements.
- Technical requirements management with business units, information security and operations.
- Coordination of external service providers, integrators and implementation partners; maintenance of project plans, milestones, resources, risks and dependencies.
- Regular reporting to project management, the program environment and internal stakeholders.
Federico L.
Last position:
Senior IAM Manager & Single Point of Contact for Information Security at EnBW Energie Baden-Württemberg AG
As Germany’s only large integrated energy company, EnBW covers the entire value chain—from energy generation and distribution to serving customers. The company is expanding its renewable energy sources, working toward a socially responsible coal phase-out, and advancing key technologies such as the use of green hydrogen. A rapid energy transition and achieving climate neutrality by 2035 are priorities for EnBW. Developing and implementing an end-to-end process view that takes both technical and organizational aspects into account Ensuring end-to-end control of all IAM-related technical services Establishing clear responsibilities and accountabilities across the IAM landscape Working with various departments to identify and optimize an end-to-end architecture and act as the Single Point of Contact (SPoC) for Information Security Introducing and monitoring governance policies to ensure compliance and security Continuously improving IAM processes and systems through regular audits and service reviews Taking part in external process audits as part of official audits against ISO standards Further developing the policy that sets administrative requirements and procedures, and aligning it with administrative departments Conceptually developing the KPI system for measuring process quality
Andreas R.
Last position:
Freelance Information Security Consultant at A-R-C Andreas Rühl Consulting
Development and implementation of customized information security strategies
Introduction and further development of ISMS according to ISO 27001, BSI-Grundschutz and other standards
Risk management and preparation of security concepts
Consulting for KRITIS, PCI DSS, TISAX and VdS 3473/10000
Establishment and optimization of security organizations
Creation and implementation of policies, guidelines, work instructions and process descriptions
Audit support and certification preparation
Delivery of training sessions, workshops and awareness campaigns
Selection and consulting for the introduction of IT security solutions such as SIEM, DLP, IDS/IPS, firewalls and encryption technologies
Conducting penetration tests and vulnerability analyses
Consulting on the selection, integration and management of security architectures in complex IT environments
Consulting on ITSM, managed security services and SOC
Management and coordination of complex projects to improve information security
Process analysis, optimization and management according to ITIL, ISO 27001 and cybernetics
Introduction and quality assurance of management, documentation and knowledge management systems
Support in complying with regulatory information security requirements (e.g. GDPR, HIPAA, SOX, GMP, KRITIS)
Development and implementation of risk analysis procedures
Organization of initial response, forensic investigations and organizational measures in security incidents
Design and delivery of targeted workshops on topics such as ISMS, IT risks and current threat scenarios
Awareness campaigns to promote a security culture in companies
Special training on ISO 27001, BSI-Grundschutz, KRITIS and other relevant standards
Simulations and exercises to prepare for information security incidents
Interim management for leading information security projects or IT security organizations
Taking on the role of external CISO (Chief Information Security Officer)
Support in developing and implementing IT security and corporate strategies
Coaching and mentoring of managers in information security
Establishment and management of security departments, including employee recruitment and qualification
Temporary assumption of management responsibility in critical situations
Daniel J.
Last position:
Information Security Consultant
NIS2 Implementation Project and ISMS Development Based on IT-Grundschutz
Municipal utilities, public-law institution
- Analysis of the current compliance status regarding the requirements of the NIS Directive (NIS-2, EU 2022/2555).
- Identification of critical infrastructures and processes within the organization.
- Development of an action plan to meet NIS requirements.
- Conducting a risk analysis in accordance with BSI Standard 200-3 as the basis for the security concept.
- Preparation of an individual security concept including technical and organizational measures according to BSI IT-Grundschutz.
- Preparatory support for an optional certification according to BSI IT-Grundschutz.
- Adaptation of existing security policies and development of new ones for access controls, incident management and data protection.
- Consideration of municipality-specific requirements and integration of the measures into the existing IT infrastructure.
- Documentation of the results and preparation of audit-ready evidence for audits.
Tools, languages and frameworks used: MS Office, Verinice, IT-Grundschutz (200-x), NIS-2 (EU 2022/2555), ISMS, AI-Act (EU 2024/1989)
Bernhard B.
Last position:
Technical Project Manager – VS-NfD Security Project
- Preparation of a complete IT security concept (ISiKo)
- Implementation of BSI / NATO / national security requirements
- Risk analysis, documentation, audit preparation
- Consulting and management of development teams in Cybersecurity Recovery and Resilience
- Genua firewalls, VPN, VS-NfD migration from Checkpoint and PaloAlto firewalls
- Administration of log sources: firewall traffic, ALG (SIP calls), ATP, DLP
- System administration – servers, AD, clients (according to BSI)
- Stakeholder communication (C-level / government agencies)
Experts recently working on similar projects
Freelancers with hands-on experience in comparable project as a Interim Project Manager
Nearby freelancers
Professionals working in or nearby Kriftel, Germany