Experience
Interim Manager, Overall Client Representative
AURUBIS AG
- Took over the project during a crisis, with a delay of approx. 1.5 years at the time of takeover in June 2024
- Clarified the contractual situation, planning and construction history, and scope of work
- Relieved the internal project management team and improved team morale
- Reassured stakeholders at all levels
- Clarified a change request with the Executive Board and Supervisory Board
- Organized problem-solving areas and developed a new schedule
- Led all subproject teams and resolved outstanding questions with the district government
- Secured approval for early construction commencement (§8a) in November 2024 and initiated construction
- Clarified safety-related aspects of the construction process
- Monitored foundation work (driven piles) and provided expert oversight
- Facilitated and coordinated weekly construction and subproject meetings
- Prevented claims initiatives
- Reported to the Executive Board and plant management
- Handed the project over to the internal project management team in an orderly manner in February 2025
Interim Managing Director
Vitronet
- Reassured employees during a crisis
- Facilitated discussions on various conflicting objectives between Vitronet and the IMD Group
- Coached the management team
- Integrated the IMD Group into the Vitronet corporate group
- Introduced a matrix organization
- Relieved the Vitronet Executive Board
- Successfully delivered critical subprojects
- Built a middle management level
- Improved financial performance through efficient process methods
- Recruited new specialists and managers
- Supported customers and framework agreement partners and renegotiated important framework agreements
- Led management and site meetings
- Managed projects in the transmission grid operator and DC cable sectors
- Accelerated construction delivery through process optimization
- Facilitated conflict resolution and mediation
- Coached emerging young leaders
- Handed over to the new management team
Interim Management, User and Investor Representative
ISAR AEROSPACE
- Led the development of a new production site and production facilities
- Coached the internal project team
- Assessed user requirements and analyzed various sites
- Held preliminary discussions with mayors and local councils to clarify planning permission issues
- Negotiated with landowners
- Initiated environmental impact assessments
- Advised on obtaining soil reports and conducting contamination assessments
- Negotiated with potential investors
- Further defined user requirements and negotiated investor offers (ROCK CAPITAL, CA IMMO, GIEAG, PANATTONI, DIBAG)
- Negotiated with the Bavarian Ministry of Economic Affairs and Finance (security arrangements)
- Prepared production and logistics planning
- Completed the project with an investor recommendation and handover to the Executive Board
Interim Manager, Overall Client Representative
NETZSCH HOLDING
- Developed and planned the new Netzsch Campus in Selb (infrastructure, facilities, real estate)
- Supported and assessed soil reports (ground improvement, contamination assessment)
- Supported and assessed environmental impact reports
- Facilitated discussions to define user requirements with department heads
- Set the schedule, planned milestones, and determined project and life-cycle costs
- Led project development and the preliminary design phase
- Set up project-specific risk management and oversaw project controls
- Assessed the feasibility of structural and architectural designs
- Led the preparation and tracking of the budget and business case
- Prepared, monitored and updated the budget, providing status reports to the shareholder
- Coached the project team in a matrix organization
- Handed over to the internal project management team
Interim Manager, Overall Client Representative
LENIO BIO GmbH
- Developed user requirements and preliminary plans for the new series production facility
- Provided expert support during contamination assessments of land and existing buildings
- Facilitated discussions to define user requirements with department heads
- Set the schedule, planned milestones, and determined project and life-cycle costs
- Led project development and the preliminary design phase
- Set up project-specific risk management and oversaw project controls
- Assessed the feasibility of structural and architectural designs
- Led the preparation and tracking of the budget and business case
- Prepared, monitored and updated the budget, providing status reports to the shareholder
Interim COO and Interim CRO, Turnaround and Project Management
FRESENIUS–HELIOS
- Took over the project with a delay of approx. 2 years on 15.08.2021
- Clarified the contract situation, planning and construction history, and scope of work
- Coached the entire project management team
- Organized problem-solving areas (fire safety, construction progress, defect rectification, commissioning)
- Introduced agile construction management methods (daily work planning, site walk-throughs)
- Coordinated weekly construction meetings using a digital Kanban board
- Held weekly one-on-one meetings with site managers and daily coaching sessions
- Increased subcontractor capacity
- Ensured construction completion and compliance with permit requirements
- Improved cost efficiency in construction delivery through Lean Construction
Interim Management, Project Lead for Crisis Management
VAMED – SANA
- Took over the project with a delay of approx. 1 year on 27.07.2020
- Clarified the contract situation, planning and construction history, and scope of work
- Coached the project and construction management teams
- Introduced agile construction management methods (daily work planning, site walk-throughs)
- Coordinated weekly construction meetings using a digital Kanban board
- Held weekly one-on-one meetings with site managers and daily coaching sessions
- Increased workforce to approx. 450 across the trades and strengthened construction management
- Ensured completion, including defect rectification, by 30.04.2021
- Improved cost efficiency in construction delivery through Lean Construction
Interim Management, Overall Client Representative
LENZE SE
- Overall client representation for the Mechatronic Competence Campus MCC
- Crisis management and project firefighting on a project delayed by > 2 years
- Facilitated the definition of user requirements with department heads
- Initiated environmental impact assessments and commissioning of expert reports
- Set the schedule and increased the budget to 53,5 Mio. € (partial approval 37,4 Mio. €)
- Evaluated and assessed delivery partners
- Restructured and streamlined the project organization
- Prepared decision recommendations for the Executive Board and Family Council
- Set up project-specific risk management and controlling
- Reviewed technical plans and execution specifications for plausibility
- Awarded construction and supply contracts, including final negotiations
- Prepared and updated the budget with status reports
- Defended against change claims
- Handover of stable investment volume, Business Case and master schedule
Interim Manager, Overall Client Representative
CONDAIR Group AG
- Led the project to commission the new plant in Norderstedt and all transfer projects
- Restructured departments, including relocating workstations
- Designed processes in production and logistics
- Led change management for the introduction of the New Work concept
- Facilitated conflict resolution between departments and functions
- Developed and partially implemented the Condair Academy in Norderstedt
- Optimized production and logistics facilities
- Developed and implemented NewWorkCulture@Condair
- Planned and delivered the new headquarters in Switzerland
- Developed and introduced global project controlling
- Organized large-group conferences and workshops
- Coached managers in line roles and project management
- Project firefighting
Interim COO and EMEA Project Manager
CONDAIR Group AG
- Planned and delivered the consolidation of four European assembly sites in Norderstedt and Pfäffikon SZ
- Facilitated the definition of user requirements and set timelines, milestones and costs
- Evaluated and assessed potential sites in Northern Germany and Central Switzerland
- Initiated and assessed soil surveys and contaminated site reports
- Led land purchase negotiations and prepared the required purchase contracts
- Set up project-specific risk management and controlling
- Reviewed construction and architectural designs for plausibility
- Reviewed and validated execution specifications
- Independently awarded construction and supply contracts and made approval recommendations
- Set and tracked the financing framework to ensure liquidity
- Updated the budget and reported status to the shareholder
- Coordinated various transfers from former production sites and commissioned the new plant
- Completed the project 2 months ahead of schedule and 1,5 Mio. € under budget
CEO / Chairman of the Executive Board
Lean Bauen Deutschland AG
- Independently managed the company
- Established 40 process teams in Germany
- Provided training and quality assurance at 650 partner companies
- Developed process-optimized planning and construction delivery procedures
- Developed and implemented agile construction delivery methods
- Established Lean practices across all construction projects
- Delivered approximately 120 commercial and industrial construction projects
- Fulfilled corporate and reporting duties to the Supervisory Board
- Ensured compliance and fulfilled other executive board duties
- Led strategic business development
Managing Director, Interim Manager and Project Manager
Luetz Management
- Managed the sole proprietorship
- Provided construction management, project controls and client representation for various private and commercial projects
- Applied and ensured the use of Lean methods in construction management
- Ensured quality and trained assigned employees
Project Manager
Allianz Real Estate AG
- Managed various refurbishment and renovation projects
- Managed integration, scope and schedules
- Managed costs, quality and communications
- Managed risks and procurement
Industry experience
See where this freelancer has spent most of their professional time.
Experienced in Construction, Manufacturing, Real Estate, Utilities, Aerospace and Defense, and Healthcare.
Business area experience
See which departments and functions this freelancer has contributed to most.
Experienced in Project Management, Quality Assurance, Operations, Procurement, Supply Chain Management, and Human Resources.
Frequently asked questions
Have questions? Find more information here.
Friedhelm is based in Eberdingen, Germany and can operate in on-site, hybrid, and remote work models.
Friedhelm speaks the following languages: German (Native), English (Advanced).
Friedhelm has at least 31 years of experience. During this time, Friedhelm has worked in at least 10 different roles and for 12 different companies. The average length of individual experience is 2 years and 4 months. Note that Friedhelm may not have shared all experience and actually has more experience.
Based on recent experience, Friedhelm would be well-suited for roles such as: Interim Manager, Overall Client Representative, Interim Managing Director, Interim Management, User and Investor Representative.
Friedhelm's most recent position is Interim Manager, Overall Client Representative at AURUBIS AG.
In recent years, Friedhelm has worked for AURUBIS AG, Vitronet, ISAR AEROSPACE, NETZSCH HOLDING, and LENIO BIO GmbH.
Friedhelm is most experienced in industries like Construction, Manufacturing, and Real Estate. Friedhelm also has some experience in Healthcare, Utilities, and Aerospace and Defense.
Friedhelm is most experienced in business areas like Project Management, Quality Assurance, and Operations. Friedhelm also has some experience in Procurement, Supply Chain Management, and Human Resources.
Friedhelm has recently worked in industries like Utilities, Aerospace and Defense, and Manufacturing.
Friedhelm has recently worked in business areas like Project Management, Operations, and Human Resources.
Friedhelm holds a Master in General Management from University of St. Gallen and a Bachelor in Civil Engineering.
Friedhelm has 4 certificates. Among them, these include: Certified Coach LINC Personality Profiler, Certified Management Consultant CMC / BDU, and Certified Scrum Professional CSP.
Friedhelm is immediately available full-time for suitable projects.
Daily rate distribution
The rates shown represent the typical market range for freelancers in this position based on recent contracts on our platform.
Average rates for similar positions
Rates are based on recent contracts and do not include FRATCH margin.
The average daily rate is the mean of all daily rates from recent contracts of comparable freelancers on our platform.
The median daily rate is the middle value of all daily rates — half of comparable freelancers charge less, half charge more. Unlike the average, it is barely affected by outliers.
Calculated based on our freelancers’ daily rates as of 27 Nov 2026. Actual rates may vary depending on seniority level, experience, skill specialization, project complexity, and engagement length.
Similar freelancers
Discover other experts with similar qualifications and experience
Ümit D.
Last position:
Managing Director at SELF Consulting und Trading Germany
- Successful integration of new business areas
- Support for change management projects
- Introduction of lean management and digitalization initiatives
- Management of external partners, interim managers, and consultants
- Successful implementation of growth and transformation strategies
- Plant expansion
- Plant relocation
Christoph H.
Last position:
Project Manager & Test Manager at Cyber Security
SAP S/4HANA upgrade from Release 2021 to 2025 and FI/CO transformation as part of a new TOM. Four streams and two SAP service providers; management during ongoing operations.
Overall responsibility for time, quality and budget as well as cross-stream coordination of the four streams
Coordination of process streams, business functions and SAP service providers
Establishment and management of governance, planning, risks, dependencies, resources and escalations
Provider management, regular management reporting, and preparation and execution of project and Steering Committee meetings
Responsibility as Test Manager for test strategy, test planning, UAT, defect management and acceptance
Result: Successful preparation for Go-live on 28.09.2026 during ongoing operations; quality and the planned absence of production interruptions ensured. Project governance established and positive feedback from management and stakeholders.
Steffen H.
Last position:
Interim CIO and IT and Business Transformation Consultant at Telelift GmbH
Started as a Business Transformation Consultant for IT and process analysis, and from 09/2025 additionally took on the role of Interim CIO with overall responsibility for IT.
- Reduced IT operating costs by 28 %.
- IT and process analysis, target vision and roadmap; governance with SLA, RPO/RTO, RACI and TOMs.
- Led the introduction of Microsoft Dynamics 365: migration, integration and connection of existing systems.
- Established reporting with Power BI; prepared decision documents and 30/60/90-day quick wins for the executive management.
Achim Z.
Last position:
Interim CDO Chief Digital Officer Universitätsklinik AKH Wien at Selbständig
Responsible for developing and implementing the digitalization strategy at AKH in Vienna
Ralph S.
Last position:
Interim Head of Business Excellence at DEHN SE
Process architect and transformation driver for company-wide excellence initiatives (covering a vacancy) Establishment and management of a company-wide process and governance framework to strengthen structure, leadership and effectiveness in an internationally growing family-owned company. Responsibility for the global process house, end-to-end governance, process role architecture and further development of the integrated management system – including international implementation (Romania, USA).
Scope:
- Management of the Business Excellence department with 6 employees and functional leadership of 20+ Process Owners
- Establishment of a global process operating system (architecture, roles, governance, global-local logic)
- Development of a group-wide control and KPI system for processes (transparency, KPIs, maturity)
- Introduction of mechanisms to ensure effectiveness in day-to-day operations (role enablement, communities, feedback)
- Governance and role framework for new production sites in Romania and USA (mandates, roles, decision logic)
- Stabilization and further development of the integrated management system (IMS)
Sustainable Results:
- Global process operating system established - Structure, roles, governance and global-local rules defined as a binding framework and anchored in the management system — the basis for consistent management and scalability.
- End-to-end process ownership strengthened - Process Owner roles globally defined, qualified and anchored in Communities of Practice — clear ownership structures across all sites for the first time.
- KPI and process management logic established - Uniform KPI system, maturity model and reporting principles developed — the basis for fact-based decisions, prioritization and transparency throughout the company.
- Effectiveness in day-to-day operations increased - Enablement architecture, onboarding mechanisms, regular meeting formats and feedback loops introduced — the process system is applied in daily work and continuously improved.
- Governance framework for new site implemented - Mandates, roles, decision paths and escalation logic for the new production site in Romania developed — clear structure for setup, management and integration.
Mirko H.
Last position:
Cybersecurity Manager at Joynext GmbH
Cybersecurity for RTCU project for the Stellantis Group.
The management of cybersecurity was strongly criticized by the customer Stellantis, questioning competence. Requirements were missing or incomplete, the architecture for cybersecurity controls was non-existent, and documentation such as cybersecurity plans and concepts were incomplete and formally incorrect.
- Building customer trust and de-escalation
- Sprint planning with the customer based on SAFe
- Task-force management
- Switching planning and control to an agile approach
- Review and update of cybersecurity documents
- Communication and problem solving with suppliers, particularly Rolling Wireless and Autocrypt
- Internal workshops and coordination across various hierarchy levels from developers to CTO
- Coordination of work packages and implementation across locations in Dresden, Ningbo, and Oborniki
- Reporting and support of cybersecurity audits
- Coaching of Joynext cybersecurity managers
- De-escalation of critical customer issues
- Acceleration of requirement creation and release by a factor of 5
- Timely provision of 3rd party components
- Reduction of vulnerability management effort by factor 3
- Creation of cybersecurity documents conformant to existing standards
- Technologies and Methods: V-Modell, ASPICE, IREB, ISTQB, Scrum, Kanban, SAFe, PMP, IPMA, BPMN 2.0, Microsoft Office, Microsoft Project, Jira, Confluence, Siemens Polarion, Dependency Track
Experts recently working on similar projects
Freelancers with hands-on experience in comparable project as a Interim Manager, Overall Client Representative
Nearby freelancers
Professionals working in or nearby Eberdingen, Germany