Experience
mobispace
- Project management of a school pavilion in timber construction (120 m² GFA) during the work preparation phase
Project Manager and Project Control, Timber Modular Construction
mobispace GmbH
The new extension to the primary school in Kappesgärten in Bensheim was handed over as a turnkey project using a modular timber construction method with 84 prefabricated modules. On the ground floor, a canteen with kitchen and a multi-purpose room offer plenty of space for learning and socializing together. Nine classrooms, open differentiation areas, and a staff room have been created on the upper floor.
The entire building is barrier-free, with an elevator and modern sanitary facilities on all floors. A photovoltaic system on the roof and DGNS certification underscore the high sustainability standards. The façade, made of pre-grayed larch wood slats, gives the new building a natural, timeless appearance.
- Construction method: Modular timber construction
- Construction site: Bensheim
- Completion: October 2025
- Construction period: 6 months
- Gross floor area: 2,335 m²
- Cost: approx. €6.1 million KG 300 + 400 net
- General contractor: mobispace GmbH
- Planning LP 1-4: werk.um architects Darmstadt
- Timber construction: Baumgarten GmbH Ebersburg
Head of Architecture, Development Manager
mobispace GmbH
- Development of a standardized modular timber construction system for school buildings, including architectural, structural, and functional systematization
- Technical management and coordination of the planning process in close cooperation with internal and external specialist planners
- Management and coordination of interdisciplinary project teams from architecture, specialist planning, execution, and external partners
- Introduction and implementation of ArchiCAD and basic BIM methods for timber modular construction projects
- Development of internal standards and optimization of digital planning and project processes throughout the entire project life cycle
In addition, Mr. Keil developed essential foundations for a company-wide, sustainable BIM concept for mobispace GmbH, which he implemented in a structured manner in order to make our planning and coordination processes sustainable and highly efficient.
project architect (LP1-8)
werk.um architects
- As project architect (LP1-8), I was responsible for coordinating the design planning, building application, implementation planning, awarding and evaluation, as well as construction and site management of the timber construction general contractor.
Architect and Project Manager, Timber
werk.um architects
- Independent handling of all service phases 1–9 in accordance with HOAI (German Fee Structure for Architects and Engineers)
- Conceptual development as well as complete project management, including cost, schedule, and quality control, as well as construction management and architectural supervision
- Development of a modular timber construction system for daycare centers, schools, and office buildings
- Defined and established design parameters for parametric planning in line with our customers’ requirements
- As part of the timber construction task force, he developed EnMurfs rules for 2D element construction and nodule construction, designed CAD basics for the BIM process, and actively participated in the design of our construction catalog
- During the implementation of ArchiCAD, he led the task force for the digital planning process, supervised the CAD team, and coordinated cooperation with external consulting firms
- Optimized and managed the implementation, documented all processes, and created a manual to ensure quality standards
Architect
Independent
LP 1-4 EFH
Project Manager, Project Architect, Construction Manager
werk.um architects
- Development and adaptation of the timber construction system for flexible office and open-space structures
- Participation, planning, and development in specific, completed projects: Hattersheim daycare center, GSI office building, Hafflochberg School, Emmendingen vocational school, IGS Vahrenheide, Kirchdittmolt School
- Responsible for coordinating planners for fire protection, HVAC, thermal insulation, sound insulation, and the timber construction development department
- Standardization of workflows, planning processes, and key details, development of a component and construction catalog
Project Architect
K76 Cooperative
The column grid construction offers flexibility in the floor plans and makes subsequent conversions easy.
- New building 2017
- Type of procedure: Direct commission
- Location: Darmstadt, Bessungen
- Facade area: 26,530 m²
- Scope: 1,450 m² living space
- Residential units: 18
- Construction costs: approx. €3 million (net)
- Start of construction: December 2015
- Completion: 2017
- As project architect (LP1-8), I was responsible for coordinating the design planning, building application, implementation planning, awarding and evaluation of contracts, as well as construction and site management.
Architect and Project Manager for Building Construction
werk.um architects
- Independent handling of all service phases 1–9 in accordance with HOAI (German Fee Structure for Architects and Engineers)
- Conceptual development as well as complete project management, including cost, schedule, and quality control, as well as construction management and architectural supervision
Project Architect
Evangelical Church in Mannheim
- As project architect, I was responsible for handling all service phases (LP 2-9), coordinating the design planning, building application, implementation planning, awarding and evaluation, as well as construction and site management.
- Type of procedure: Multiple commission in a cooperative procedure, 1st prize, 2009
- Scope: just under 1,000 sqm NF
- Construction costs: €5 million (gross)
- Structural engineering: Dr. Kreutz+Partner, Nuremberg
- Landscape architects: Club L94, Cologne
Project Architect
netzwerkarchitekten
Architect
r-m-p passivhaus architects
Working student
Passive House Institute
Architect
Kämpfen Sustainable Architecture
Working student
Passiv House Institute
Project Manager and Architect
werk.um architects
The apartment building in Zurich, built in 1938, is part of a perimeter block development and was renovated in 2010 to become the first Minergie-P-eco certified apartment building. The measures included extension of the entire north facade using modular timber construction. In addition, a roof maisonette was added to the building, a ventilation system was planned, ecological materials were used, and an elevator was installed.
Industry experience
See where this freelancer has spent most of their professional time.
Experienced in Construction, Education, and Professional Services.
Business area experience
See which departments and functions this freelancer has contributed to most.
Experienced in Project Management, Product Development, and Quality Assurance.
Frequently asked questions
Have questions? Find more information here.
Christian is based in Darmstadt, Germany.
Christian speaks the following languages: German (Native), English (Intermediate).
Christian has at least 23 years of experience. During this time, Christian has worked in at least 10 different roles and for 11 different companies. The average length of individual experience is 1 year and 5 months. Note that Christian may not have shared all experience and actually has more experience.
Based on recent experience, Christian would be well-suited for roles such as: Project Manager and Project Control, Timber Modular Construction, Head of Architecture, Development Manager, project architect (LP1-8).
In recent years, Christian has worked for mobispace, mobispace GmbH, werk.um architects, and Independent.
Christian is most experienced in industries like Construction, Education, and Professional Services.
Christian is most experienced in business areas like Project Management, Product Development, and Quality Assurance.
Christian has recently worked in industries like Construction and Education.
Christian has recently worked in business areas like Project Management, Product Development, and Quality Assurance.
Christian holds a Master in Architecture from TU Darmstadt.
Christian is immediately available for suitable projects.
Daily rate distribution
The rates shown represent the typical market range for freelancers in this position based on recent contracts on our platform.
Average rates for similar positions
Rates are based on recent contracts and do not include FRATCH margin.
The average daily rate is the mean of all daily rates from recent contracts of comparable freelancers on our platform.
The median daily rate is the middle value of all daily rates — half of comparable freelancers charge less, half charge more. Unlike the average, it is barely affected by outliers.
Calculated based on our freelancers’ daily rates as of 27 Nov 2026. Actual rates may vary depending on seniority level, experience, skill specialization, project complexity, and engagement length.
Similar freelancers
Discover other experts with similar qualifications and experience
Robert M.
Last position:
Project Engineer, Architect, Construction Manager
Expansion and Conversion Measures - Pharmaceutical
Official completion of the 2022 extension building for approval by the authorities.
Review of the design, preparation of the outstanding bills of quantities and awarding of the construction work. ...
Frank J.
Last position:
Senior Project Manager / IT Manager - Email Gateway Migration & Information Security at Public Authority
- Strategic planning, detailed technical preparation and operational management of an email gateway migration in a security-critical government environment.
- Preparation of the technical specification and development of technical concepts and migration approaches in line with BSI requirements.
- Technical requirements management with business units, information security and operations.
- Coordination of external service providers, integrators and implementation partners; maintenance of project plans, milestones, resources, risks and dependencies.
- Regular reporting to project management, the program environment and internal stakeholders.
Thorsten H.
Last position:
OCM (Overall Construction Manager) for HVAC at Engie Deutschland GmbH
- Overall planning and supervision of the relevant HVAC and sanitation installations across multiple construction phases.
- Leading installation teams and subcontractors.
- Ensuring adherence to schedules, budgets and quality standards.
- Coordination with other trades.
- Lean Construction Management, preparing and moderating the Last Planner Method.
- Supporting schedule planning and moderating workshops in the IPA project environment.
- Planning, organizing and supervising all HVAC and sanitation work on site.
- Managing own installers and coordinating subcontractors.
- Ensuring that all work meets quality standards, safety regulations and the schedule.
- Aligning with other trades, authorities and the client representative.
- Creating plans and reviewing invoices.
- Monitoring the proper application of construction techniques and compliance with safety regulations.
Wilhelm L.
Last position:
Construction/Project Management Building Services at Jakob Ebling GmbH
- Cloud HQ data center in Offenbach
- Construction cost: approx. EUR 1 billion
- Blackhat
- Smoke extraction system
- Commissioning of refrigeration systems
- Coordination of work permits and access authorizations
Friedhelm L.
Last position:
Interim Manager, Overall Client Representative at AURUBIS AG
- Took over the project during a crisis, with a delay of approx. 1.5 years at the time of takeover in June 2024
- Clarified the contractual situation, planning and construction history, and scope of work
- Relieved the internal project management team and improved team morale
- Reassured stakeholders at all levels
- Clarified a change request with the Executive Board and Supervisory Board
- Organized problem-solving areas and developed a new schedule
- Led all subproject teams and resolved outstanding questions with the district government
- Secured approval for early construction commencement (§8a) in November 2024 and initiated construction
- Clarified safety-related aspects of the construction process
- Monitored foundation work (driven piles) and provided expert oversight
- Facilitated and coordinated weekly construction and subproject meetings
- Prevented claims initiatives
- Reported to the Executive Board and plant management
- Handed the project over to the internal project management team in an orderly manner in February 2025
Kolja K.
Last position:
Project Management for Residential and Commercial Properties at Quartier Heidestraße GmbH & Co. KG
Renovation work and conversions for commercial tenants
- Technical specification of the work
- Time and cost management
- Management of customer requirements
- Contract awards and service provider management
Experts recently working on similar projects
Freelancers with hands-on experience in comparable project as a
Nearby freelancers
Professionals working in or nearby Darmstadt, Germany